Projects in Progress Fall 2017

Posted on: October 11, 2017 5 AM

ACC HAYS CAMPUS PHASE 2 – KYLE, TX
New Construction Roofing
Contract Amount: $550,000 (approx.)
Owner: Austin Community College District
Architect: Pfluger
General Contractor: Vaughn Construction
Scope of Work: Installation of TPO roofing, standing seam roofing, joint sealants, sheet metal flashing and trim
Project Description: Training facility for law enforcement students

ORACLE WATERFRONT – AUSTIN, TX
New Construction Waterproofing
Contract Amount: $2,500,000 (approx.)
Owner: Oracle
Architect: TBG Architects + Planners
General Contractor: Ryan Companies
Scope of Work: Installation of below-grade waterproofing, hot fluid-applied waterproofing, air barrier, metal flashing, joint sealants, structural glazing, expansion joints, epoxy coating, traffic coating, pavers and pedestals
Project Description: Office complex for a multinational computer technology corporation

METHODIST HOSPITAL TNI PARKING GARAGE – SAN ANTONIO, TX
Remedial Waterproofing
Contract Amount: $1,600,000 (approx.)
Owner: Methodist Healthcare System
Consultant: Raba Kistner
General Contractor: Chamberlin Roofing & Waterproofing
Scope of Work: Concrete repair, structural injection, replacement of expansion joints, traffic coating, water repellent, joint sealants and bearing pads
Project Description: Renovation and repair of parking structure

HERMANN PAVILION 2 – HOUSTON, TX
New Construction and Remedial Roofing & Waterproofing
Contract Amount: $4,300,000 (approx.)
Owner: Memorial Hermann Health System
Architect: WHR Architects
General Contractor: Vaughn Construction
Scope of Work: Tie in existing roof to the wall of new building and to new roof, installation of modified bitumen roofing, PVC roofing, sheet metal flashing, coping, below-grade concrete repair, structural epoxy injection, below-grade bentonite and cold fluid-applied waterproofing, crystalline waterproofing, fluid-applied waterproofing, traffic coating and site sealants
Project Description: Hospital expansion

OKLAHOMA UNIVERSITY CROSS VILLAGE RESIDENTIAL – OKLAHOMA CITY, OK
New Construction Waterproofing
Contract Amount: $1,500,000 (approx.)
Owner: BBCS Development, LLC
Architect: Studio Architecture
General Contractor: JE Dunn Construction
Scope of Work: Installation of dampproofing, sheet waterproofing, vehicular traffic coating, water repellents, spray-applied air barrier, acoustical sealants, site and paving sealants, firestopping, joint sealants and expansion joints
Project Description: Luxury on-campus student housing

GABLES UPTOWN TRAIL – Dallas, TX
Remedial Waterproofing
Contract Amount: $900,000 (approx.)
Owner: Gables Construction, Inc.
Architect: Wiss, Janney, Elstner Associates, Inc.
General Contractor: Chamberlin Roofing & Waterproofing
Scope of Work: Concrete patching, waterblasting, cement plastering, painting and replacement of coating, joint sealants and expansion joints
Project Description: Upscale multi-family housing

THE EPIC: DEEP ELLUM – DALLAS, TX
New Construction Waterproofing
Contract Amount: $1,000,000 (approx.)
Owner: Westdale Properties America I, Ltd.
Architect: Perkins + Will
General Contractor: Balfour Beatty
Scope of Work: Installation of hot fluid-applied rubberized asphalt waterproofing, sheet waterproofing, pre-applied sheet waterproofing, cementitious and reactive waterproofing, pedestrian traffic coatings, thermal insulation, spray-applied air barrier, sheet metal flashing and trim, flexible flashing and joint sealants
Project Description: A multi-purpose complex including office, multi-family housing and hotel space

DURANT TRIBAL COMPLEX – DURANT, OK
New Construction Waterproofing
Contract Amount: $400,000 (approx.)
Owner: Choctaw Nation
Architect: JCJ Architecture, Inc.
General Contractor: Manhattan Construction
Scope of Work: Installation of site and paving sealants, joint sealants, sheet waterproofing and traffic coating
Project Description: Choctaw Nation's Headquarters

FROST TOWER – SAN ANTONIO, TX
New Construction Waterproofing
Contract Amount: $700,000 (approx.)
Owner: Frost Bank
Architect: Pelli Clarke Pelli Architects
General Contractor: Clark Construction
Scope of Work: Installation of below-grade waterproofing, hot fluid-applied waterproofing, air barrier, joint sealants, fire sealants, expansion joints and sheet metal flashing
Project Description: State-of-the-art office building and new headquarters
for Frost Bank

WESTSIDE LEXUS – HOUSTON, TX
Remedial Waterproofing and New Construction Roofing & Waterproofing
Contract Amount: $1,700,000 (approx.)
Owner: FR – Lexus II Limited
Architect: Goree Architects
General Contractor: Wier Enterprises
Scope of Work: Standing seam roofing, PVC roofing, decor rib roofing, sheet metal and flashing, below-grade waterproofing in elevator pits, removal of traffic coating on existing structure and installation of new traffic coating, traffic coating at new parking garage, site and exterior building sealant
Project Description: Renovation of existing exterior parking garage, addition of new multilevel parking garage and expansion of car dealership

Subscribe Today!

Stay-in-the-know and subscribe to our blog today!