### **New Hidalgo County Courthouse - Edinburg, TX**

 New Construction Waterproofing    
Contract Amount: $1,150,000 (approx.)   
Owner: Hidalgo County   
Architect: HDR Architecture, Inc.   
General Contractor: Morganti Texas, Inc.   
Scope of Work: Installation of sheet waterproofing, traffic coatings, air barrier, sheet metal flashing, flexible flashing, firestopping and joint sealants

 Project Description: County courthouse

### **Comal High School #5 - San Antonio, TX**

 New Construction Waterproofing   
Contract Amount: $1,650,000 (approx.)   
Owner: Comal Independent School District

 Architect: Pfluger   
General Contractor: Bartlett Cocke   
Scope of Work: Installation of hot applied waterproofing, sheet waterproofing, water repellents, insulation, air barrier, sheet metal flashing, drip edge flashing, pavers and pedestals, firestopping, joint sealants, site sealants and expansion joints   
Project Description: Public high school

### **TCU Hyatt Place - Fort Worth, TX**

 New Construction Roofing and Waterproofing   
Contract Amount: $1,000,000 (approx.)   
Owner: Campus Hotel Venture   
Architect: GPF Architects   
General Contractor: Jordan Foster Construction   
Scope of Work: Installation of roof pavers, TPO roofing, flashing and sheet metal, counterflashing, gutters, cap wall and curb flashings   
Project Description: Hotel on college campus

### **HCA Medical Center - Exterior Facade Repair - Houston, TX**

 Remedial Waterproofing

 Contract Amount: $800,000 (approx.)   
Owner: HCA 

 Architect: Perkins and Will   
General Contractor: O'Donnell/Snider Construction    
Scope of Work: Power washing, cut out and re-caulking of expansion joints, wet glazing of windows, tuck-pointing of mortar joints and installation of window perimeter sealants and elastomeric coating   
Project Description: Hospital

### **Holdsworth Center - Austin, TX**

 New Construction Roofing   
Contract Amount: $2,500,000 (approx.)   
Owner: Charles Butt, Chairman of HEB   
Architect: Lake|Flate Architects   
General Contractor: Beck Commercial Construction, LLC   
Scope of Work: Installation of hot modified roofing, wood blocking, coping, gutters and sheet metal roofing   
Project Description: Leadership institute campus

### **Grapevine Rail Station Hotel - Grapevine, TX**

 New Construction Waterproofing   
Contract Amount: $400,000 (approx.)   
Owner: PMM Hotel Partners 2017 LP

 Architect: Architexas   
General Contractor: Manhattan Construction Company   
Scope of Work: Installation of sheet metal flashing and trim, metal underlayments, air barrier, cementitious and reactive waterproofing, firestopping, joint sealants and expansion control   
Project Description: Marriott Autograph Collection Hotel

### **Piedmont at River Oaks - Houston, TX**

 Remedial Roofing and Waterproofing   
Contract Amount: $3,700,000 (approx.)   
Owner: Piedmont at River Oaks HOA   
General Contractor: Building Engineering Consultants, Inc.   
Scope of Work: Removal of modified bitumen roofing and installation of wood blocking, hot modified roofing, TPO roofing, flashing and sheet metal, exterior rainscreen drainage composite, fluid-applied waterproofing, new three-coat stucco, window replacement, exterior elastomeric coating, balcony handrail restoration, wall flashing and joint sealants   
Project Description: Condominium complex

### **Union Stadium East Renovations - Tulsa, OK**

 Remedial Waterproofing   
Contract Amount: $150,000 (approx.)   
Owner: Union Public Schools

 Architect: Dewberry Architects   
General Contractor: Crossland Construction   
Scope of Work: Installation of traffic coatings, air barrier, firestopping and joint sealants   
Project Description: Football stadium

### **The Center of Hearing and Speech - Houston, TX**

 New Construction Roofing   
Contract Amount: $400,000 (approx.)   
Owner: The Center of Hearing and Speech

 Architect: Inventure Design   
General Contractor: Tellespen   
Scope of Work: Installation of wood blocking, curb flashings, TPO roofing, PVC membrane roofing, flashing and sheet metal   
Project Description: Full service resource for deaf children

### **TFC North Austin Complex - Austin, TX**

 New Construction Waterproofing   
Contract Amount: $400,000 (approx.)   
Owner: Texas Facilities Commission   
Architect: STG Design    
General Contractor: Vaughn Construction   
Scope of Work: Installation of drainage composite, fluid-applied waterproofing, below-grade insulation, flashing and sheet metal, firestopping, joint sealants, paving sealants and expansion control   
Project Description: Health services commission headquarters

 

### [See What Our Clients Are Saying](https://www.chamberlinltd.com/testimonials-list/)

[View full post](https://www.chamberlinltd.com/articles/summer-2020-pips)

```json
{
  "@context" : "http://schema.org",
  "@type" : "BlogPosting",
  "author" : {
    "@type" : "Person",
    "name" : "Admin"
  },
  "dateModified" : "2021-07-23T19:18:41.347Z",
  "datePublished" : "2020-06-30T05:00:00Z",
  "headline" : "Summer 2020 PIPs",
  "image" : {
    "@type" : "ImageObject",
    "height" : 288,
    "url" : "https://f.hubspotusercontent10.net/hubfs/19521315/Imported_Blog_Media/facebook-drop-icon-chamberlin-Jul-23-2021-07-17-58-67-PM.png",
    "width" : 170
  },
  "mainEntityOfPage" : "https://www.chamberlinltd.com/articles/summer-2020-pips",
  "publisher" : {
    "@type" : "Organization",
    "logo" : {
      "@type" : "ImageObject",
      "height" : 60,
      "url" : "/hs/hsstatic/content_shared_assets/static-1.4092/img/default-amp-logo.png",
      "width" : 60
    },
    "name" : "Chamberlin - Articles"
  }
}
```