2015 Winter Projects in Progress

Dylan Apartments – Dallas, TX
Remedial Waterproofing
Contract Amount: $1,500,000 (approx.)
Owner: Canyon Capitol Reality Advisors, LLC
Consultant: Wiss, Janney, Elstner Associates, Inc.
General Contractor: Chamberlin Roofing & Waterproofing
Scope of Work: Dampproofing, elastomeric coating, spray air barrier, joint sealants, veneer plastering, painting, flashing and coping
Project Description: Luxury apartments and townhomes

KC 46A Hangar McConnell – McConnell AFB, KS
New Construction Waterproofing
Contract Amount: $250,000 (approx.)
Owner: U.S. Army Corps of Engineers
Architect: Burns & McDonnell
General Contractor: Archer Western Aviation Partners
Scope of Work: Dampproofing, bentonite waterproofing, air barrier, firestopping, joint sealants and expansion joints
Project Description: Three hangars to house KC-46 Pegasus tanker fleet

Oil & Gas Technology Center – Oklahoma City, OK
New Construction Waterproofing
Contract Amount: $450,000 (approx.)
Owner: GE Global Research
Architect: Miles Associates
General Contractor: Flintco, LLC
Scope of Work: Below-grade sheet waterproofing, air barrier and joint sealants
Project Description: GE and Devon Energy’s technology center

Baylor Stadium – Waco, TX
New Construction Waterproofing
Contract Amount: $1,500,000 (approx.)
Owner: Baylor University
Architect: Populous, Inc.
General Contractor: Austin Commercial
Scope of Work: Air barrier, firestopping, roof coating, joint sealants, flashing, expansion joints and metal sub roof
Project Description: McLane Football Stadium

The Methodist Hospital Research Institute – Houston, TX
Remedial Waterproofing
Contract Amount: $250,000 (approx.)
Owner: Houston Methodist Hospital
Architect: WHR Architects
General Contractor: Chamberlin Roofing & Waterproofing
Scope of Work: Removal of existing waterproofing and installation of new topping slab, cold applied waterproofing membrane, rigid insulation and concrete pavers
Project Description: Twelfth floor terrace renovation

Houston Methodist Sugar Land – Sugar Land, TX
New Construction Roofing
Contract Amount: $1,000,000 (approx.)
Owner: Houston Methodist Hospital
Architect: Watkins Hamilton Ross Architects
Consultant: Zero-Six Consulting, LLC
General Contractor: Vaughn Construction
Scope of Work: Modified bitumen roof system, sheet metal flashing and metal panel entry canopy
Project Description: Bed tower and cath lab

Homewood Suites Garage Renovation – San Antonio, TX
Remedial Waterproofing
Contract Amount: $150,000 (approx.)
Owner: Chatham San Antonio, LLC
Architect: DLR Group
General Contractor: Swinerton Builders
Scope of Work: Elastomeric and traffic coating
Project Description: Parking garage for hotel and downtown customers

Baylor College of Medicine (CNRC) – Houston, TX
Remedial Waterproofing
Contract Amount: $950,000 (approx.)
Owner: Baylor College of Medicine
Consultant: Zero-Six Consulting, LLC
General Contractor: Chamberlin Roofing & Waterproofing
Scope of Work: Demolition and removal of existing tiles, topping slab and waterproofing; installation of new hot-applied waterproofing membrane, rigid insulation and concrete pavers
Project Description: Children’s Nutrition Research Center

Knox Park – Dallas, TX
New Construction Roofing and Waterproofing
Contract Amount: $500,000 (approx.)
Owner: Knox Apartments Owner, LLC
General Contractor: MCRT North TX/Mountain States Construction, LLC
Scope of Work: Single ply roof system, flashing and coping, blindside waterproofing, fluid applied waterproofing, fire sealant and elevator pit waterproofing
Project Description: Multi-family residence

Indigo Hotel – Austin, TX
New Construction Waterproofing
Contract Amount: $300,000 (approx.)
Owner: 9th Red River, LLC
General Contractor: Journeyman Construction
Architect: Mitchell Carlson Stone, Inc.
Scope of Work: Below-grade and cold fluid-applied waterproofing, elevator pit waterproofing, traffic coating, air barrier and joint sealants
Project Description: 10-story hotel