2013 WINTER Projects in Progress

Dallas Convention Center – Dallas, TX
Remedial Waterproofing
Contract Amount: $1,500,000 (approx.)
Owner: City of Dallas
Architect: HKS Architects
General Contractor: Chamberlin Roofing & Waterproofing
Scope of Work: Hot fluid-applied waterproofing, sheet waterproofing, concrete repair, expansion joint replacement, joint sealant replacement
Project Description: Multi-level exhibition and meeting facility

Texas State Performing Arts Center Complex – San Marcos, TX
New Construction Waterproofing
Contract Amount: $500,000 (approx.)
Owner: Board of Regents of the Texas State University System
Architect: Morris Architects
General Contractor: Hunt Construction
Scope of Work: Water repellent, elastomeric coating, crystalline waterproofing, concrete sealer, below-grade sheet and cold fluid-applied waterproofing, dampproofing, sheet metal and flexible flashing, joint and site sealants, firestopping and expansion joints
Project Description: Parking garage, recital hall, theatre and central plant

Arts & Technology Building – Dallas, TX
New Construction Roofing
Contract Amount: $850,000 (approx.)
Owner: Board of Regents of University of Texas System
Architect: VAI Architects, Inc.
General Contractor: Hunt Construction Group
Scope of Work: Modified roofing systems, standing seam metal roof and flashing
Project Description: The University of Texas at Dallas visual arts & technology building

George Bush Intercontinental Airport – Terminal B Southside Replacement – Houston, TX
New Construction Waterproofing
Contract Amount: $700,000 (approx.)
Owner: Continental Airlines
Architect: PGAL Architects
General Contractor: Skanska USA, Inc.
Scope of Work: Thermal insulation, fluid-applied membrane air barriers, sheet metal flashing and trim and joint sealants
Project Description: Renovation of new and existing passenger facilities at Terminal B

Chickasaw Nations Visitors Center – Sulphur, OK
New Construction Waterproofing
Contract Amount: $100,000 (approx.)
Owner: Chickasaw Nation Department of Commerce
Architect: Frankfurt Short Bruza (FSB)
General Contractor: Flintco
Scope of Work: Air barrier, bentonite waterproofing, joint sealants and water repellents
Project Description: Chickasaw National Recreation Area

Terminal A Enhanced Parking Structure – Dallas, TX
Remedial Waterproofing
Contract Amount: $2,000,000 (approx.)
Owner: Dallas-Fort Worth Airport
Architect: Corgan Associates, Inc.
General Contractor: Austin Commercial
Scope of Work: Sheet waterproofing, concrete sealer, expansion joints, joint sealants, deck sealer and firestopping
Project Description: Airport parking garage renovation

Tinker Air Force Base Bldg. 3001 – Midwest City, OK
Remedial Waterproofing
Contract Amount: $200,000 (approx.)
Owner: United States Air Force
Architect: Pinnacle Design Group
General Contractor: The Ross Group Construction Corp.
Scope of Work: Cut out and re-caulk parapet cap sealants, elastomeric coating of parapet cap and new entry canopies, tuck pointing and water repellents
Project Description: 1,300,000 sq. ft. aircraft maintenance and refurbishing building

River Oaks Medical Center – Houston, TX
Remedial Roofing & Waterproofing
Contract Amount: $450,000 (approx.)
Owner: MPT of Twelve Oaks, L.P.
Architect: PGAL
Consultant: ZERO/SIX Consulting
General Contractor: Hoar Construction, LLC
Scope of Work: Modified roofing and sheet metal, joint sealant replacement and elastomeric coating
Project Description: Eight story hospital

Lackland ACC Phase 1B – San Antonio, TX
New Construction Waterproofing
Contract Amount: $400,000 (approx.)
Owner: US Army Corps of Engineers
Architect: Hoefer Wysocki Architects, LLC
General Contractor: JE Dunn Construction
Scope of Work: Below-grade waterproofing, air barrier, joint sealants, flashings and expansion joints
Project Description: Ambulatory Care Center at Lackland Air Force Base

Exxon Computing Facility – Spring, TX
New Construction Roofing
Contract Amount: $1,400,000 (approx.)
Owner: Palmetto Transoceanic, LLC
Architect: Gensler
Consultant: French Engineering
General Contractor: Gilbane|Harvey
Scope of Work: New single-ply roofing system with associated sheet metal flashings
Project Description: 31,000 sq. ft. computer facility